kyle.ryan@LIGO.ORG - posted 16:05, Tuesday 30 October 2012 (4559)
Corner Station instrument air restored to nominal configuration
Replaced all drying tower check-valves and solenoid valves as well as solenoid valve coils -> most of these components were original (1997) and overdue for replacement -> original desiccant will be replaced too but is on back-order at this time