Weekend Commissioning: 25 W work, looking at PI Modes (Seb & Terra)
Tues Maintenance Work Summary: Stay in Laser Hazard & 4Hrs (i.e. end at noon)
- PSL/IO
- PZT swap by Jason, Cheryl, Keita (no other PSL work can go on until this work done! Coordinate with HAM3 ISI work, if needed)
- DBB work by Jason
- Robert would like to do measurements after PZT swap
- Dust Monitor move in Diode room (Jeff B)
- HAM3 ISI Noise Hunting of ~1Hz thing (Hugh)
- IMC need to go OFFLINE if this happens, so will need to coordinate with PSL work.
- CDS:
- ESD work at EX & EY
- Temperature sensors into PCal to look for noise
- Model Work
- OMC Model Change (Keita)
- HAM4/5/6 HEPI & ISI model updates (Hugh)
- TCS Model Change: Simulation fix (Danny)
- LSC POPDC channels (Daniel)
- ECAT CS 4 Only Beckhoff Restart (Daniel)
- PCal Work: Calibration & Tune Up. Start with EY. (Rick)
- VAC
- MY hammer drilling, extra vehicle traffic
- MX annulus ion pump (this week)
Safety: Be careful with icy conditions!