Reports until 16:19, Thursday 13 December 2018
H1 General
yannick.lecoeuche@LIGO.ORG - posted 16:19, Thursday 13 December 2018 (45915)
Shift Summary - Day

TITLE: 12/13 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC

STATE of H1: Commissioning

INCOMING OPERATOR: None

SHIFT SUMMARY:

14:50 (6:50) Rick and Sudarshan to EY -- End station calibration

15:20 (7:20) Chris to MX -- scaffold setup

16:00 (8:00) Phiffer on site

16:00 (8:00) Start of shift

16:35 (8:35) Karen to EY

16:40 (8:40) Fil, Ed to EX

16:47 (8:47) Karen leaving EY

16:53 (8:53) Richard to LVEA -- check out ALS fibers

16:54 (8:54) EY back to laser safe

17:12 (9:12) Richard out of LVEA

17:17 (9:17) Karen to LVEA

17:27 (9:27) Vanessa to LVEA

17:27 (9:27) Ed, Fil back from EX

17:31 (9:31) Chris to LVEA -- grab scaffolding

17:45 (9:45) Richard to CER

17:58 (9:58) Chris out of LVEA

18:05 (10:05) Vanessa out to LVEA, going to EX, MX

18:45 (10:45) Nutsinee to ISCT6

18:56 (10:56) Chandra to LVEA

18:59 (10:59) Nutsinee out of LVEA

21:45 (13:45) Chris to MX

22:26 (14:26) Nutsinee to ISCT6

22:29 (14:29) Chris back from MX

00:00 (16:00) End of shift