TITLE: 01/09 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Commissioning
INCOMING OPERATOR: None
SHIFT SUMMARY:
LOG:
- Corey covered most of the day, see his alog 46282 here:
- continuing the log:
- TCS: chiller swap was a no-go, current chiller remains in service until a replacement chiller pump is located/purchased
- RF MEASUrEMENTS: continued until MX gate valves were restored to the open position
- SQZ: HAM6 work continue, done for today
- EE: Fil finished the ground wire at EY, and went to EX. Shared that he had en encounter with some ALS cables/fibers, which was very helpful for understanding changes seen during the recovery of H1
- BOOTFEST: is complete
- CDS: DaveB was done early afternoon
- SEI: Jim restored HAM and BSC ISI's by the end of the day
- GRD: TJ completed guardian updates, and tested BIG EARTHQUAKE before departing
- Bubba returned from the LVEA
- Fil returned from EX
- Nutsinee and and Terry returned from HAM6/LVEA
- Robert went to EX to make measurements around 5PM, currently there as of 6:30PM