Displaying report 1-1 of 1.
Reports until 18:47, Wednesday 07 November 2012
LHO General
patrick.thomas@LIGO.ORG - posted 18:47, Wednesday 07 November 2012 - last comment - 10:15, Thursday 08 November 2012(4619)
Ops Summary
PAC meeting
Rick, Cheryl, installation of light pump, alignment of optics between laser enclosure and HAM1.
Sensor failure for dust monitor in Bake Oven Room.
Hugo reported DAC channels not writing correctly for h1seih23, frontend rebooted.
HAM2 viewport installation
Filiberto dressing cables in cable trays around HAM3
Operator station alarm handler moved to H1

Two visible earthquakes on seismic plots:
5.1	54km SW of Champerico, Guatemala	2012-11-07 22:42:48 UTC	13.907°N	92.225°W	35.1 km
7.4	24km S of Champerico, Guatemala	        2012-11-07 16:35:50 UTC	14.083°N	91.916°W	41.6 km
Comments related to this report
patrick.thomas@LIGO.ORG - 10:15, Thursday 08 November 2012 (4638)
The dust monitor that failed is labeled 'P'. It has been pulled and is being sent out for repair.