Schedule as of the end of the meeting, for 15 Jan 2019: Tentative
- 7AM: SEI Proc & SEI ISI corner boots - Jim
- 8:30AM: Lock IMC
- 9AM: IO path on the PSL, IO_MB_M3, replace optic and damp the high Q
- 11AM: ASC Model/Boot
- DEFERED TO WED: Guardian Machine Swap
Activities:
- ASC Model Update
- SEI corner ISI Model boots, sensor correction
- EY Pcal Meas
- CALEX model work
- TCS model update
- Temp Sensor fix on Pcal
- TEMP P.S. EX ESD
- HAM2 Handrail
- move HAM5/6 CR ~2'
- ISS 2nd loop QPD centering, per Gabriele's alog (done today, Monday)
- SRM SWC Setup @ HAM5
- EY HWS beam align - NEEDS EY optics, hardware, software, to be unchanged during this activity
- PEM inventory walkabout
- Table top FSS P.S.HDWR @ SQZ table
- ground measurements at EX
- Damp PSL/IO (2x) optics/mounts, and swap M3 optic
- HAM2/3 inspection measurements
- swap out TCSY chiller with spare
- RF/ground loop hunting
- Trend writer work
Images of the very full white board attached.