Reports until 16:14, Monday 04 February 2019
H1 General
yannick.lecoeuche@LIGO.ORG - posted 16:14, Monday 04 February 2019 (46777)
Shift Summary - Day

TITLE: 02/04 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC

STATE of H1: Commissioning

INCOMING OPERATOR: None

SHIFT SUMMARY:

 

14:40 (6:40) Chris traveling arms to assess tumbleweed buildup

16:00 (8:00) Start of shift

17:45 (9:45) Hugh to EX -- look at anemometer

17:46 (9:46) Terry to Optics Lab

17:55 (9:55) Marc, Fil to Vault -- PEM system calibration

18:04 (10:04) Terry back from Optics Lab

18:12 (10:12) Kyle to MY -- wiring on prototype vacuum equipment

18:18 (10:18) Hugh back from EX

18:34 (10:34) Patrick to MSR

19:07 (11:07) CALEX, CALEY restart

19:13 (11:13) Vanessa to EX, EY, MY

19:43 (11:43) Kyle back from MY

20:00 (12:00) Marc, Fil back from Vault

22:00 (14:00) Nutsinee to LVEA

23:19 (15:19) Nutsinee out of LVEA