BSC1 (Cartridge)
-
Cartrdige/ITMy Alignment work (Doug): requiring Laser Hazard soon---MAKE SURE TRANSITION CORRECTLY!!!
-
Cartridge Insertion: Not today most likely (prep)
-
Prism Photo Survey (Margo/Kate):
-
Cleanroom/Platform moves (Bubba)
-
Cabling Satelite -> feedthrus in the morning (Filiberto)
-
Dial Indicators (Hugh)----wait for after Robert
PSL/IO:
-
PSL Table: New spacers under PSL Periscope
-
HAM2 work
-
Michael turns laser ON at 9:47am
Septum viewport install HAM1/2
Viewports installed on top of HAM2 (center & north)
BSC2 Cartridge
-
Mass pulled
-
cable routing
-
float
Optical Lever (need for Robert's test)
-
transmitter complete
-
receiver being installed for ITMy (Thomas & Jax)
DAQ Work
-
h1daq restart (for slow controls)
-
front ends going down (as bring in new front ends)
-
lsc & asc
EX--clean & dome ready to be removed (maybe this afternoon)
Bubba said, "Clean stainless is being loaded into bin"
The LVEA is now in LASER HAZARD from about 10am - 1pm.
EY Dust Alarm (gerardo, worden, jodi)---note: Access System is not communicating to EY & EX
EY Chiller Yard alarm (due to Robert measurements)
Maintenance:
Pallets picked up near Staging (two loads)
Fire Dept on site.