Commissioning update: Longer locks hitting 100Mpc seems to be more common, the ITMX RO OSEM maybe causing some issues.
Tuesday:
Fac - EX is now accessible for nitrogen delivery tomorrow. EY will need some plowing, starting this morning.
HFD will be on site.
Vac - Vendor starting work at MY, but also checking spots in most buildings but not VEAs. This work will continue all week.
MY electronics finish.
PEM - Moving magnetometers to many locations.
PCal - EY measurement.
CDS - ITMX RO OSEM investigation.
Model restarts: SEI (see below), h1sqz, h1asc, EY Beckhoff
SEI - h1hpi/h1isi(ey/ex)/h1seiproc models restart. DAQ restart needed as well. (Take all platforms to safe state.)
HEPI accumulator quarterly check, platforms will be down.
PSL - Bullseye sensor troubleshooting.
TT FSS box, mirror count.
HWS - Temperature sensor install.