gregory.mendell@LIGO.ORG - posted 17:15, Friday 01 March 2019 (47234)
Updated DMT production computers to gstlal-calibration-1.2.8

As per WP 8104 and SCCB issue 82, I have updated the DMT production computers to gstlal-calibration-1.2.8. For example, this allows pcal correction factors that are applied to GDS strain to be updated from the front end for ER14. See: https://git.ligo.org/sccb/requests/issues/82.

I have not restarted the DMT calibration code. No changes have taken place yet.

When H1 is down, I have asked Aaron Viet to restart the DMT calibration code and put in an alog. This should not affect FOMs in the control room.

(More DMT/GDS updates are scheduled for next Tuesday maintenance, on March 5, as per WP 8106.)

 