Reports until 07:50, Wednesday 05 December 2012
H2 FMP
jodi.fauver@LIGO.ORG - posted 07:50, Wednesday 05 December 2012 (4838)
BSC5 ICC
This entry is for activity that occurred on Tuesday, 04 Dec 2012.
Viewports, etc. removed from chamber. Condition of chamber documented. Support tubes wrapped and bellows protection installed. Brushing of collar complete by the end of the day.