EX
In-chamber cleaning continues
New HVAC system for the Lab is now online after being serviced today
BSC1
Hugh & Vincent worked on/around cabling up on the BSC-ISI to troubleshoot some noise on the BSC-ISI
IO Work
The team planned on checking torque-ing for MC2 (requiring HAM3 ISI to be locked), and alignment work continues (so we've remained in Laser HAZARD all day)
Rest of Day's Activity
-
H&N Electric on site to fix sewage lift pump at LSB
-
Elec Inspector going to EX (will go with Ken)
-
Since last night, we had a PSL alarm for Envdiode Temp Alarm (Rodruck notified and addressed)
-
Oscar & group baling on inside of X-arm
-
Filiberto routing field cables at BSC2
-
Patrick--addressed dead dust monitor in LVEA (replaced with one from EY)
-
Bubba removing lock & tag from GV1
-
Praxair on site to fill CP1
-
HAM4 & 5 doors being torqued down (in prep for pumpdown)