Reports until 15:46, Monday 10 December 2012
H1 General
justin.bergman@LIGO.ORG - posted 15:46, Monday 10 December 2012 (4876)
Ops Shift Summary
•	PSL diode room temperatures continuing to fluctuate between 65F and 70F, producing alarms. This has been an ongoing issue since 6DEC. Michael R has 
        made adjustments to the heating units for the room and this should help.

•	0700 Work is ongoing in and around BSC1. Bolts on the dome flange were torqued first thing this morning by Apollo---tripped ITMY SUS watchdogs.

•	0930 Kyle opening GV-1

•	1100 Travis S et al removing First Contact from ITMY---unsurprising SUS watchdog trips.

•	1300 Thomas V and Jax S working on optical lever alignment in LVEA.

•	1330 Bubba craning cleanroom over HAM9 to prep for MC tube inspection.

•	1450 Dave B and Jim B to MX.

•	1500 All LVEA dust monitors went INVALID---Patrick was investigating.