LHO FMCS
bubba.gateley@LIGO.ORG - posted 12:25, Thursday 02 May 2019 - last comment - 15:38, Thursday 02 May 2019(48936)
END Y AHU 1 LINKAGE
At ~ 1015 hrs local time, I got an alarm that the temperature at E Y was ~ 1 degree F. above set point. I started to investigate and things were just not looking correct on my FMCS screen. I confirmed with the control room operator that I was able to go to the end station and upon entering the building, I immediately noticed the sound was not what it normally is. I looked in the air handler room and the F/B damper was completely closed. I looked at the linkage which was in an obvious bind so I forced the damper open and the temperature immediately started to stabilize. I will continue to closely monitor the temps and hope to re-adjust the linkage on Tuesday morning unless it is needed sooner.   
Comments related to this report
thomas.shaffer@LIGO.ORG - 15:38, Thursday 02 May 2019 (48944)

Just for reference, the attached screenshot is what we saw from the control room today. Time 0 was at 10 this morning.

Images attached to this comment
Displaying report 1-1 of 1.