IO Crew (I assume) was out at HAM2/3 most of the day (aligning/installing baffles)
-
Filiberto & G2 continue HAM4 Cable Pulling
-
Blank Flange installation at HAM7/8
-
8:10 Hanford Fire Dept investigating alarm at MX
-
9:11 Street sweeper on site (starting at corner & then Yarm)
-
9:15 Thomas heading out for Oplev stuff (out for hours
-
9:15 Laser group (w/ Rodruck) heading to H1 PSL (PMC measurement & water connection work [assume this was what caused several min of 100+dust counts])
-
~10 Pre-filter installation at all out-buildings complete (no dust alarms for any of this work)
-
11:05 Barton starting MC1 transfer functions (for an hour or so)
-
11:00 Dust 14 & 15 went INVALID for a few minutes
-
10:30 - 12:30 Jodi out of HAM8/9, but Robert still taking pictures in there
-
1:19 received Hanford site test of emergency system phone call
-
Laser Hazard at 2:00pm (coinciding with Laser Training)
-
4:15 Hugo is unlocking HAM3-ISI for the IO group
Toward the end of shift I heard rumblings of rebooting HAM-AUX (requested by IO group & performed by Dave)