Reports until 07:49, Friday 14 December 2012
H2 INS
jodi.fauver@LIGO.ORG - posted 07:49, Friday 14 December 2012 (4930)
BSC5 ICC
Yesterday, the Apollo finished wipe down, second vacuum, chamber FTIRs, and close-out inspection. Two doors were returned to the chamber, one torqued. This morning, the technical cleaning crew is doing first cleaning on the dome cleanroom. Once that is complete, the cleanroom will be moved over the dome and second cleaning will be done. The Apollo crew will move the dome spreader from the OSB to X-end and start torquing the remaining door bolts. After second cleaning, the dome will be cleaned. If time permits, we'll try for putting the dome on today.