Reports until 15:32, Friday 14 December 2012
corey.gray@LIGO.ORG -
posted 15:32, Friday 14 December 2012 (4931)
-
6.3mag earthquake in Baja Calif at 2:36am
-
Optical Levers: (Robert, Thomas) Another calibration measurement (cover removed from viewport)
-
Cheryl/IO checking ifo beam alignment on beam dump at HAM2
-
Ski swapping prefilters for OSB area (including Optics Lab, Bake Oven Room---Cleanrooms/flow benches will be functioning, but will monitor dust monitors). This took about 10min.
-
Surprise expressed at ITMy whose Sattelite Box was powered off last night (this was Robert last night for field tests). Satelite box powered back up and ITMy damped.
-
HAM2 SUS Watchdogs reconnected to SEI HAM2 &3.
-
Michael & Oliver turned off the laser to do work on the water distribution system
-
Ski may cause FMCS alarms at mid-stations