TITLE: 06/04 Day Shift: 15:00-23:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Commissioning
INCOMING OPERATOR: Cheryl
SHIFT SUMMARY:
Maintenance day went well. The remainder of the day was used by commissioners to work on adding and optimizing DRMI ASC loops.
LOG:
1515:01 GRBV alert
15:04 Lockloss - Sheila induced
15:16 Sheila out to optics lab or squeezer bay to look for beam profiler
15:17 Sensor correction turned off at end stations.
15:18 Chris taking pest control into LVEA
15:21 Kyile out to MY - WP 8226
15:24 Fil out to pull cable from HAM5/6 to CER - climbing on chambers
15:25 Niko and Driptha out to EY for PCal work
15:26 Fire System maintenance on site
15:34 Dave B turning off Fire Pump Cell Phone notices until noon
15:36 EY to LASER HAZARD
15:46 Chris and pest guys back
15:47 Richard out to LVEA HAM5/6 area
15:52 IMC_LOCK guardian is now OFFLINE and unmanaged at Dr Kissel's request.
15:55 Richard back
15:57 Dick out to LVEA and CER for measurements
15:58 Karen leaving EY
15:58 Vanessa out to LVEA
16:03 Karen out to MY
16:09 Amber called about tour coming to CR around 10:00ish
16:10 Christina out to LVEA
16:23 Hugh heading out to EY to tend wind Fence
16:30 Karen leaving MY
16:30 Coffey Refigeration coming through gate - Jeff Bartlett
16:31 Norco on site - dewar 71
16:40 Rick and Laurence out to EY
16:50 Betsy and Sheila out to LVEA
17:09 Norco on site(second load) _ dewar 77
17:12 Vanessa back and heading out to EX
17:32 Marc out
17:35 Richard out to roof
17:36 Pest control done
17:39 Gerardo out to LVEA
18:00 Tour into control room
18:10 Initial Alignment re-locking ALS
18:10 Kyle back from MY
18:13 Sensor correction re-engaged
18:17 Niko out to optics lab
18:22 Input Align - following ALS attention
18:51 Begin locking
18:55 Daniel and Patrick out to LVEA
20:17 Pep out to CER to move a magnetometer
20:22 Pep back