Displaying report 1-1 of 1.
Reports until 16:04, Thursday 20 January 2011
H2 DAQ
corey.gray@LIGO.ORG - posted 16:04, Thursday 20 January 2011 (497)
BSC8 Door & Dome Removed In Prep For Seismic Isolation De-Install

[Chris, Corey, Hugh, Jim, Kyle, Zach]

The BSC8 Door was removed.  Jim entered chamber and removed the (18) inside Support Tube bolts.  Dome was removed, and Chamber was covered.  De-install & re-install of Dome will occur tomorrow.

Displaying report 1-1 of 1.