Quarterly HEPI Accumulator Check/Recharge--Not at EndX

Per WP 8256, took SEI systems down at the Corner and independently at Endy, to check the fluid accumulators' gas charge.  Not one accumulator needed charging in the corner station nor at EndY.  Did not attempt EndX as Pcal work was going on.

Then EndX will not take very long, maybe 1 hour and we'll do that as soon as tolerable.  I'll venture that the 7 accumlators at EndX will be fine but that venture will likely be all it takes to insure that at least one will need charging so better plan on checking.

Comments related to this report
hugh.radkins@LIGO.ORG - 14:10, Tuesday 02 July 2019 (50351)

Did EndX Accumulators today.  Were it not for the gas loss when I got the gauge stuck on the valve on one unit on the Pump Station, no accumulator on the site needed charging this quarter.