X Arm and X End status
The tumbleweed situation on X Arm remains dicey. One lane was cleared from the corner to the end however there has been some encroachment due to subsequent weather. The road section from the corner to the mid is a little intimidating because of the height of the tumbleweed piles but is passable as long as you don't hurry too fast. The road section from the mid to the end is somewhat more open. 

ICC is complete, the new spool pieces are installed and married up and all doors are returned to the chamber.