Reports until 15:42, Thursday 10 January 2013
H1 General
justin.bergman@LIGO.ORG - posted 15:42, Thursday 10 January 2013 (5070)
Ops Shift Summary
•	0700 LVEA in laser hazard all day.

•	0700 Y-end: Overhead Door crew onsite all day. Dust counts occasionally non-zero as fans are disengaged. 

•	0900 Y-end: Dale, Jodi, Terry, and Christina filming contamination control video. From the overhead cameras the cinematography looks excellent.      
             Inspired acting but plot difficult to follow. Would have been better with a love interest. 3 stars.

•	0930 Cheryl V and I/O team working in and around H1PSL enc and HAM1. Frequent dust alarms.

•	0930 Apollo crew working on finalizing septum hardware install (BSC2/HAM4) 

•	0900 Hugh installing last bellow on HAM6

•	1045 Jim B power-cycling I/O chassis in LVEA (H1SEITST)

•	1100 Filiberto working inside laser curtains at HAM1 (shutter is closed)

•	1130 Hugo running control loops at HAM2, possibility of shaking cleared with Chris Mueller and Cheryl 

•	1145 Bubba and crew installing feedthroughs on BSC9 (WP 3644)

•	1230 Jim B heading to MX to begin work on PEM racks (seismometer front ends)

•	1245 Dave B restarting multiple SUS models as well as LSC and DAQ

•	1245 Richard inspecting equipment along Y-beam manifold and power-cycling H1SEITST (this subsequently took the SUS test stands offline for a bit).

•	1330 Travis and Betsy working in BSC1. ITMY watchdog trips.

•	1345 Patrick evaluating H0 alarm values (DUST, FMCS, Weather) and doing BURT restore to make sure correct settings were put in place following the 
             equipment move from the H2 building. Air handlers at EY immediately started alarming with the new “old” values---the roll-up door is open for 
             maintenance.