Indicated He baseline of 4.5 x 10-10 torr*L/sec at start -> 10 second audible blast at each conflat joint and 5 second audible blast in volume between each window and corresponding guard shutter Note: There is still an untested electrical feed-through flange on south side of HAM2 between the support tubes but it is not accessible