Reports until 16:00, Thursday 15 August 2019
H1 General
travis.sadecki@LIGO.ORG - posted 16:00, Thursday 15 August 2019 (51294)
Ops Day Shift Summary

TITLE: 08/15 Day Shift: 15:00-23:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Corrective Maintenance
INCOMING OPERATOR: Ed
SHIFT SUMMARY:  Commissioning all shift attempting to recover locking.  Still in progress.
LOG:

16:17 Still unable to get past DRMI ASC

16:18 Commissioners to LVEA to measure IMC open loop gain

16:29 Commissioners out

17:26 Jason to optics lab

17:57 Jason out

18:36 Niko and Ethan to PCal lab

18:59 Niko, Ethan out

21:36 Niko, Ethan to PCal lab

21:42 Adrian, Matt to CER moving PEM cables

21:43 NIko, Ethan out