Tomorrow 8am the one month long commissiong break will start.
We will have a 1pm Wednesday Vent meeting.
See the white board for entire the Trello plan for the vent, or see the link on G1901314. It is colored for different types of activities. Brief outline for this week, but please see Trello for the full schedule:
- Monday - Prep day for anything that won't affect observation.
- Tuesday - Begin venting and prepping for doors.
- Clean HAM6 area, set up scafolding, move ISCT6.
- Laser safe for chambers.
- Vaccuum spools prep.
- Wednesday - HAM6 doors open. SQZ fiber install begin. Vacuum work continue/start.
- Thursday - BRS upgrade start. SQZ, Vac work continued.
- Friday - All mork continues.
Other notes:
- Communications fiber contractor on will be on site.
- HFD will also be on site.
- CDS starting up backup machine for all slow FMCS, Beckhoff, Vac channels for the vent.
- Phase camera on ISCT1.
- See work permits for the rest of the activities.