Ops Shift Transition: 10/01/2019, Day Shift 15:00 – 23:00 (08:00-16:00) - UTC (PT)
State of H1: Planned Engineering
Intent Bit: Commissioning
Weather: 0-5 mph wind
Primary 0.03 – 0.1Hz: 0.01 um/s
Secondary 0.1 – 0.3Hz: 0.1 um/s
Outgoing Operator: Corey
Quick Summary: Starting October commissioning month, IFO down, lasers being shuttered, SC off