TITLE: 10/03 Day Shift 15:00 – 23:00 (08:00-16:00), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY: Updated PT-180 software, turbo replacement underway, XBT manifold pump down underway, PSL work ongoing, ISCT1 prep done
LOG:
Tyler, Chris, Kyle, to LVEA -- start spool work, misc. Work
15:10 (08:10) Chub, Jordan to LVEA -- assist VAC team
15:54 (08:54) Jason to Optics Lab
16:04 (09:04) Patrick finished with PT-180 software upgrade
16:15 (09:15) Jason out of Optics Lab
16:33 (09:33) Sheila to SQZT6 -- check alignment
16:33 (09:33) Dan to LVEA -- prep for ISCT1 work
16:37 (09:37) Gerardo to LVEA -- assist Kyle
16:47 (09:47) Chris, Tyler out of LVEA -- crane work done
17:10 (10:10) Tyler to LVEA
17:13 (10:13) Karen to woodshop
17:31 (10:31) Tyler out of LVEA
17:33 (10:33) Gerardo to MY -- grab tools
17:56 (10:56) Tyler to LVEA -- start craning old turbo
17:57 (10:57) Gerardo back from MY
18:02 (11:02) Jason, Georgia to PSL enclosure -- continue ALS bypass pick-off work
18:05 (11:05) Betsy to LVEA -- find Chandra
18:05 (11:05) Handing off to Cheryl
activities: 18:10UTC to 20:27UTC
20:27 (13:27) Taking over for Cheryl
20:37 (13:37) Vanessa to LVEA
20:57 (13:57) Chris to LVEA -- find Tyler
21:38 (14:38) Jason, Georgia to PSL enclosure -- continue pick-off work
21:42 (14:42) Chub, Jordan to end station -- take cryopump measurements
21:44 (14:44) Tyler out of LVEA