chandra.romel@LIGO.ORG - posted 15:43, Friday 11 October 2019 (52430)
GV1 & GV2 are now open

Slowly opened GV1 and then GV2 to combine the vertex with YBM and XBM volumes. Accidentally burped in dry purge air from GV1 gate annulus because outer o-ring leaks (when vertex was vented) and this caused YBM turbo to trip and YBM pressure to rise to e-5 Torr. YBM turbo is now spun down and scroll off; vertex turbo is pumping the entire corner station, backed by scroll. Shut down QDP80 and flushed header with purge air.