H2 INS
corey.gray@LIGO.ORG - posted 16:26, Thursday 03 February 2011 (525)
Leveling HAM10 Support Tubes & Removing HAM10 Support Table

[Bubba, Corey, Hugh, Nicole, Scott]

After surveying work yesterday (level of the Support Tubes), we leveled up the Support Tubes via the Scissors Tables.  Once this work was done, we pulled out the Support Table so Jodi could go in and do some fit checks for cleaning work.  The Support Table is still out, and will hopefully get re-installed on Fri.