Reports until 15:48, Wednesday 16 October 2019
H1 SEI (PEM)
hugh.radkins@LIGO.ORG - posted 15:48, Wednesday 16 October 2019 (52519)
Wind Fence Update--Drilling Complete--Concrete Shoe Tomorrow

All the drilling and casing placement is complete.  Photo shows last casing at EndY.  Tomorrow, Thursday, concrete delivering will arrive on-site ~10:30 to pour a 12" thick plug, foot, shoe, in the bottom of the casing upon which the pole will sit. And that will be it for this phase of the wind fence.

Images attached to this report