corey.gray@LIGO.ORG - posted 11:03, Monday 21 October 2019 (52589)
Mon 9am Site Coordination Meeting Notes
SAFETY:
Watch for animals on road.
Recent vehicle collision involving a fatality (due to vehicle trying to pass group of cars)
Benton Country sheriff on site Thurs for "active shooter" inspection. Will later write a document on this subject to be gone over at a future site meeting.
Coordination Activities:
VAC: On schedule. 2-3 significant tasks:
YBT turbo (~2day) (kyle)
changing of pump config equilibrium (requires sign-off on rga scan) (kyle)
OMC NEG pump (need to condition NEG pump which requires climbing up high) (gerardo)
HAM6 RGA bake-out (kyle)
Instrument Air (bubba)
Gate Valves due to open Thurs. 10/24
FACILITIES:
Crane Maintenance here Wed & Thurs (bubba)
NCAL Drilling (bubba)
Possible clean room work is a maybe
HAM6 Scaffold removal after VAC need
Craning a forklift over BT
Wind Fence: No contractors/work until 2nd week of Nov
SEI:
cleaning A+ actuator wire in fume hood (vanessa & hugh)
A+ extraction needs tooling...maybe this week
BRS work (resolving software issues) (Jim, Patrick)
HEPI maintenance, but requires taking H1 down
HAM2 Camera work (cheryl)
Possible CDS Model restarts: SEI (bug fix), PSL ISS, SEIPROC)
Corner station switch work?
COMMISSIONING
SRM guoy phase measurement possibly today
SQZ/HAM6 area work
ALS End Stations work
Phase camera
New HWS laser set for remote operation at EY (Richard)
NCAL/IAS: Final check for holes on BSC pier for Bubba to drill.