Reports until 11:03, Monday 21 October 2019
corey.gray@LIGO.ORG -
posted 11:03, Monday 21 October 2019 (52589)
Mon 9am Site Coordination Meeting Notes
SAFETY:
- Watch for animals on road.
- Recent vehicle collision involving a fatality (due to vehicle trying to pass group of cars)
- Benton Country sheriff on site Thurs for "active shooter" inspection. Will later write a document on this subject to be gone over at a future site meeting.
Coordination Activities:
- VAC: On schedule. 2-3 significant tasks:
- YBT turbo (~2day) (kyle)
- changing of pump config equilibrium (requires sign-off on rga scan) (kyle)
- OMC NEG pump (need to condition NEG pump which requires climbing up high) (gerardo)
- HAM6 RGA bake-out (kyle)
- Instrument Air (bubba)
- Gate Valves due to open Thurs. 10/24
- FACILITIES:
- Crane Maintenance here Wed & Thurs (bubba)
- NCAL Drilling (bubba)
- Possible clean room work is a maybe
- HAM6 Scaffold removal after VAC need
- Craning a forklift over BT
- Wind Fence: No contractors/work until 2nd week of Nov
- SEI:
- cleaning A+ actuator wire in fume hood (vanessa & hugh)
- A+ extraction needs tooling...maybe this week
- BRS work (resolving software issues) (Jim, Patrick)
- HEPI maintenance, but requires taking H1 down
- HAM2 Camera work (cheryl)
- Possible CDS Model restarts: SEI (bug fix), PSL ISS, SEIPROC)
- Corner station switch work?
- COMMISSIONING
- SRM guoy phase measurement possibly today
- SQZ/HAM6 area work
- ALS End Stations work
- Phase camera
- New HWS laser set for remote operation at EY (Richard)
- NCAL/IAS: Final check for holes on BSC pier for Bubba to drill.
- PCal EY checking beam alignment (niko)