Reports until 12:23, Friday 25 January 2013
H1 IOO
joseph.gleason@LIGO.ORG - posted 12:23, Friday 25 January 2013 (5262)
IOT 2 Components Installed for SM2T and PRMR Beams
All of the components have been installed on IOT 2 with their final optics except for the Trans Mon PD. Some small deviations were made from  the layout D0902284.

1) The IO_SM2T_GIGE2 camera was moved to the left of IO_SM2T_GIGE1 to avoid the periscope base similar to what was done at LLO.

2) IO_PRMR_BS1 and IO_PRMR_BS2 were turned to send dump the beam toward the chamber in order to use right handed mirror mounts.

There were some issues installing the patch panel blanks, not all of which fit properly. The mounting holes for them are of very close fit and probably need to be drilled slightly larger. I have left the screws out in these places. Also on the left side, one of the large panels was too wide to fit and will need to be machined down slightly.

At this point the table is considered clean space and access requires proper garb. Also the HEPI fan must be kept running.
I've marked off the cutout for the beam penetration and arranged with Kiwamu to have that machined. The opening will need to be covered with plastic as with the other tables when the panel is removed for machining. I've also arranged with apollo to have the aluminum spacers installed to lift the table to the "LHO" height.
Images attached to this report