Displaying report 1-1 of 1.
Reports until 18:44, Tuesday 22 October 2019
LHO VE
kyle.ryan@LIGO.ORG - posted 18:44, Tuesday 22 October 2019 (52634)
YBM turbo installation -> Found 2 x 10-8 torr*L/sec leak (helium) at the rotatable turbo fixation/6-way cross joint

Gerardo M., Kyle R.

Bummer!  We were so close!  We'll start the day tomorrow addressing this leak. 