Reports until 15:45, Friday 25 January 2013
LHO VE
kyle.ryan@LIGO.ORG - posted 15:45, Friday 25 January 2013 (5271)
HAM6 bellows leak testing -> Retested NE bellows -> OK
Observed a delayed signal response initially this morning when retesting the NE bellows -> Pumped annulus volume and applied instrument air to external leak test ports closest to NE bellows -> Retested -> OK  

HAM6 bellows pass leak testing.