TITLE: 10/28 Day Shift 15:00 – 23:00 (08:00-16:00), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY: Locked shortly after shift start, lost lock around 10:30. Had trouble re-locking, Sheila aligned IM3 and PR3 to increase COMM beatnote. Lost lock again about 2.5 hours later, likely due to PEM injections. Re-locking, currently at ACQUIRE_DRMI_1F.
LOG:
15:06 (08:06) Tyler driving forklift outside corner station
15:11 (08:11) Tyler finished
15:42 (08:42) Vlad to Optics Lab
16:53 (09:53) Robert, Phillipe to LVEA
16:54 (09:54) Jeff to mechanical room - check TCS chillers
16:58 (09:58) Patrick to H2 -- IO chassis testing
17:03 (10:03) Hugh to Optics Lab -- open fume hood for evaluation
17:04 (10:04) Jeff back from mechanical room
17:30 (10:30) Lockloss from NLN
17:55 (10:55) Timesh, Gavin to EX -- pick up NCAL equipment
18:04 (11:04) Richard to MX, MY -- find cable
18:24 (11:24) Timesh, Gavin back from EX
18:25 (11:25) Timesh, Gavin to Optics Lab -- drop off equipment
18:27 (11:27) Richard back from mid-stations
18:29 (11:29) Timesh, Gavin back from Optics Lab
18:56 (11:56) Patrick back from H2 building
19:17 (12:17) Robert, Dan to LVEA -- look at ISCT1
19:26 (12:26) Robert, Dan out of LVEA
19:29 (12:29) Jeff, Charles to Optics Lab -- look at chemicals
19:30 (12:30) Patrick to H2 building -- continue testing
19:46 (12:46) Patrick back from H2
19:48 (12:48) Hugh, Jeff out of Optics Lab
21:44 (14:44) Sheila, Lee to LVEA -- look for GPIB adapter near PSL racks
22:03 (15:03) Betsy to Optics Lab
22:35 (15:35) Sheila to LVEA -- clear out troublemakers
22:40 (15:40) Sheila out of LVEA