Reports until 14:54, Tuesday 03 December 2019
H1 SEI (SYS, VE)
hugh.radkins@LIGO.ORG - posted 14:54, Tuesday 03 December 2019 (53658)
H2 HAM7 A+ SEI Transport Fixturing added, continued

continuing from 5 Nov, alog 53026:

Jack & Hugh WP 8384.  Brought in the north crane and disconnected the HAM7 N. Crossbeam from the HEPI housings.  Pulled the crossbeam and got the radius plates connected to the U-Chan and Chamber.  This is not completely secure yet.  We ran out of maintenance time and need to shim.  Attached photo shows the progress

Images attached to this report