michael.rodruck@LIGO.ORG - posted 16:40, Tuesday 05 February 2013 - last comment - 19:13, Wednesday 06 February 2013(5379)
Ops day summary
Cyrus working on upgrading switches. This took out communication from the medm screens to the frontends for most of the morning, but everything has come back up
Unifirst on site
Praxair delivered to CP2
Paradise water on site
Kiwamu and Max working on the ALS fiber pick off from the reference cavity
Dave edited the h1iopseib6IOP
Betsy working on the beamsplitter
Michael L and Apollo removed ETMY optic
Michael L gave tour in LVEA
Comments related to this report
patrick.thomas@LIGO.ORG - 19:13, Wednesday 06 February 2013 (5398)