H1 SEI
hugh.radkins@LIGO.ORG - posted 13:26, Tuesday 04 February 2020 (54892)
H2 HEPI Removal & Transport Fixturing Installation Progress --HAM7 Complete HAM8 1/2 Done

WP 8384 ScottL & HughR

Following on from last Tuesday, we got the U-Channels onto the Support Tubes and the RAdius Plates installed beween the chamber and the U-Channel of HAM7 S and HAM8 N.  HAM7 is complete as far as the Transport Tooling is concerned, ready for jacking and craning.  HAM8 is half finished with the North Crossbeam removed and Support Tubes fully secured to the chamber.  3 Crossbeams done, 5 to go.  Photos--HAM7 Ready, HAM8 1/2 way there.

Images attached to this report