H1 SEI
hugh.radkins@LIGO.ORG - posted 15:31, Tuesday 25 February 2020 (55299)
H2 HEPI Removal & Transport Fixturing Installation Progress --HAM7 and now HAM8 Done

WP 8384 Gerardo & Hugh, continuing from 54892:

Missed two weeks on this task but made up for that today.  HAM8 South Crossbeam removed but still needs crane & laydown.  Support Tubes all secure & SEI is ready for Transport.

Thanks to Gerardo for the much needed assists.

Photo is from the East side with South side to left.

Images attached to this report