Reports until 13:14, Friday 22 February 2013
H1 INS
jodi.fauver@LIGO.ORG - posted 13:14, Friday 22 February 2013 (5564)
BSC2 Install Prep
Bubba, Mark L. and Eddie determined ideal placement of the four sections of the work platform yesterday. Today, the crew carefully craned the sections into place (mostly very tight spaces) around the chamber: this involved removing some cable trays and accelerometer plates so sections would fit. (Thank you, Richard and Hugh.) The sections were coupled together and then braces were installed to maintain some space between the work platform and HEPI.