jodi.fauver@LIGO.ORG - posted 14:34, Tuesday 26 February 2013 (5582)
BSC2 Install Prep Checklist
Work Platform in place-Done
Cleanroom in place-Done
E-module in place (Beer garden)-Done
Add hand-rail to e-module
Build custom bridge between work platform and e-module
Move garbing/staging cleanroom from spool area to top of e-module
Move cleanroom from HAM aux optics table to BSC2-HAM3 for garbing/staging
Work on cleanroom curtains-Started 26 Feb 2013
Check cleanroom function
Clean chamber and cleanrooms
Stage garbing/staging cleanrooms
Baffle assembly (Clean test stand-solid stack to test stand ~28 Feb-Shelving units moved out-work tables moved in-clean cleanroom and contents prior to assembly start)