Reports until 15:46, Wednesday 27 February 2013
H1 INS
jodi.fauver@LIGO.ORG - posted 15:46, Wednesday 27 February 2013 (5599)
BSC2 Install Prep Checklist
Build custom bridge between work platform and e-module
Install central curtains on garbing/staging cleanroom
Move cleanroom from HAM aux optics table to BSC2-HAM3 for garbing/staging
Work on cleanroom curtains: "doorway" at bridge?
Clean chamber and cleanroom X 2
Check cleanroom function
Stage garbing/staging cleanrooms
Baffle assembly (Clean test stand-solid stack to test stand ~28 Feb-work tables moved in-clean cleanroom and contents prior to assembly start)