Displaying report 1-1 of 1.
Reports until 16:00, Tuesday 22 February 2011
H2 INS
patrick.thomas@LIGO.ORG - posted 16:00, Tuesday 22 February 2011 (564)
Ops Day Summary
Dave fixed a problem with the email alarms not getting sent to cell phones. The cron job on GC was not running.
Richard and Cyrus worked on resolving issues with the access control system losing communication to end X.
The electrician looked at End X, Mid X and LVEA circuits for Richard.

Unifirst Delivery 8:45
Paradise Water Delivery 9:20
Sprague 9:26
Tumbleweed bailing finished 2:13

The test of the vacuum pump degrouting will not take place until next week.
Displaying report 1-1 of 1.