Lower level garbing/staging cleanroom moved into place and central curtain installed Dome bolts removed 2nd cleaning at BSC2 Dome bolts removed (Additional cleaning complete.) Leg jacks tested Work on crane rails complete Baffle assembly (work tables craned over beam tube, cleaned, moved into cleanroom) Still need to: Remove dome Check chamber cleanroom function Stage garbing/staging cleanrooms