Reports until 13:32, Monday 04 March 2013
H1 INS
jodi.fauver@LIGO.ORG - posted 13:32, Monday 04 March 2013 (5646)
BSC2 Install Prep Checklist
Lower level garbing/staging cleanroom moved into place and central curtain installed
Dome bolts removed
2nd cleaning at BSC2
Dome bolts removed (Additional cleaning complete.)
Leg jacks tested
Work on crane rails complete
Baffle assembly (work tables craned over beam tube, cleaned, moved into cleanroom)

Still need to:
Remove dome
Check chamber cleanroom function
Stage garbing/staging cleanrooms