Reports until 07:56, Wednesday 06 March 2013
H1 INS
jodi.fauver@LIGO.ORG - posted 07:56, Wednesday 06 March 2013 (5674)
BSC2 Install Prep Checklist
This report is for yesterday.
Dome was removed
Walking plates were wiped down and put into place
Both staging cleanrooms were populated
Chamber cleanroom function was checked (2 fan-filter units were on low rather than high, 1 fan-filter unit was not functioning and was replaced)