Reports until 16:20, Wednesday 06 March 2013
H1 SYS
hugh.radkins@LIGO.ORG - posted 16:20, Wednesday 06 March 2013 (5689)
WBSC2 Cartridge (ISI & BS SUS) installed in Chamber

No issues to report here.  We had only 5 Apollo crew.  Cleanroom was lowering at 8am and the Cartridge was TDC at 1155.  Crane full payload was 9560, Cartridge weight 9130lbs (less the 430lb 3point lifter).  Apollo took 30 minute lunch and back to raising the cleanroom.  Landed and bolted to Support tubes and all torqued, closed up, & exited at 1445.

Thanks to Jodi for lots of prep work as well as Jim Greg & Mitchell and Apollo: Randy, Mark, Mick, Scott & Ed.  Thanks to MichaelL for logistical & moral guidance.

I'm sure Dale will provide to images soon.