Reports until 15:26, Thursday 07 March 2013
H1 INS
jodi.fauver@LIGO.ORG - posted 15:26, Thursday 07 March 2013 (5711)
BSC2/HAM3 Cleanroom Marriage
Randy and crew tried unsuccessfully to crane the cleanroom over the valve on the ion pump. After consultation with John, the cleanroom legs were raised 6 inches and the cleanroom move was tried again with success. HAM3 cleanroom was butted right up to the BSC2 cleanroom but at a slight offset to accommodate the power box and leg casters. HAM3 cleanroom curtains were adjusted to fill gaps: additional curtain work will be done in the morning. The cleanroom was powered up and turned on: FFU function will be checked in the morning. First cleaning was done and west door bolts were removed except for the usual four, which were loosened. The lower level garbing/staging cleanroom was moved to allow west door access. The forklift was craned over the beam tube so it can be used for door removal.

Hard cover was returned to BSC2 after Hugh's brief entry this morning.