Reports until 14:23, Tuesday 12 March 2013
H1 INS
jodi.fauver@LIGO.ORG - posted 14:23, Tuesday 12 March 2013 (5765)
X End status
Assembly of Buffer cleanroom completed and cleanroom moved into place.

Randy and I checked to see what preparations were needed to facilitate ETMX install and discussed a possible sequence of events. Below is a first attempt at a checklist.Please email me any additions/corrections and I will post this checklist periodically.

1. Find BSC5 dome leak (Apollo)-In progress
2. Install Work Platforms at BSC9/Walking Plates setting on Work Platforms? (Apollo/Jodi)
3. Move BSC cleanroom over BSC9 (Apollo)
4. Assemble and place E-module including upper garbing/staging cleanroom (Apollo/Jodi)
5. Determine test stand location (IAS/Michael L./Jodi)
6. Get BSC ISI and Quad into VEA (SEI/SUS/Apollo)
7. Assemble Test Stand cleanroom (Apollo)
8. Move Work Space cleanroom into VEA/Nest cleanrooms (Apollo)
9. Get engine hoist into VEA? (Apollo)
10. Assemble Test Stand (Apollo)
11. Level Test Stand (IAS?)
12. Gross clean Test Stand (Tech Cleaners)
13. Place lower level support cleanrooms-Test Stand, Work Space, Garbing/Staging (Apollo)
14. Clean all cleanrooms (Tech Cleaners)
15. Move ISI to Test Stand (SEI/Apollo)
16. Level, balance and test ISI (SEI)
17. Marry SUS to ISI (SUS/Apollo)
18. SUS check-out (SUS)
19. Remove dome and doors (Apollo)
20. Install cartridge (SEI/Apollo)